Sampling and lead times

From an approved tech pack: proto 5–7 days, fit 3–5 days, PP 5–7 days. Once you approve the PP sample, fabric and production take 15–30 days to ex-factory, for orders up to 10,000 pieces. Each stage ends in an approval — nothing moves forward until you sign it off. Samples cost $20 per sample, which covers shipping it to you.

End to end: From an approved tech pack, the published stages add up to 28–49 days to ex-factory: proto, fit and pre-production samples, then fabric and production.

The critical path, stage by stage
StageDurationWhat it depends on
Proto sample5–7 daysFrom an approved tech pack. First physical read on fit and construction.
Fit sample3–5 daysAfter your comments on the proto. More fit rounds extend this stage.
PP sample5–7 daysPre-production sample in bulk fabric and trims. Nothing is cut before you sign it off.
Fabric and production15–30 daysFrom your PP sample approval to ex-factory, for orders up to 10,000 pieces. Custom dye or print takes longer, and larger orders get their date with the quote.

What actually moves these dates

Extends the schedule

  • Extra fit rounds — each one adds its own cycle
  • Custom dyeing or printing instead of stock fabric
  • Lab dip and strike-off re-approvals
  • Trims or hardware with their own lead time
  • Comments returned slowly — the clock is shared

Shortens it

  • A complete tech pack: measurements, BOM, artwork, label copy
  • Stock fabric in an available colour
  • Consolidated feedback in one round rather than three
  • Approving a counter-sample instead of re-specifying
Treat a single number as a warning sign. A supplier who answers "about 60 days" without naming the milestones has not planned your order — they have guessed. Ask any supplier, including us, what their lead time assumes about fabric availability and approval rounds.

Questions about samples and lead times

How long does the first sample take?

5–7 days from an approved tech pack. The fit sample follows in 3–5 days after your comments, and the pre-production sample in 5–7 days. Samples cost $20 per sample, which covers shipping it to you.

How long is production after PP approval?

15–30 days from your PP-sample approval to ex-factory, fabric and production included, for orders up to 10,000 pieces. Larger orders get their date with the quote.

What is the total from tech pack to ex-factory?

From an approved tech pack, the published stages add up to 28–49 days to ex-factory: proto, fit and pre-production samples, then fabric and production. Transit time depends on the route, port and carrier, so we give it with your quote.

What delays a timeline?

Extra fit rounds, each with its own cycle; custom dyeing or printing instead of stock fabric; lab dip and strike-off re-approvals; trims or hardware with their own lead time; and comments returned slowly. Custom fabric also changes the minimum: 50 pieces is achievable on stock fabrics. Custom dyeing or printing carries the fabric mill's own minimum, which is higher — we confirm the real minimum against your fabric before quoting.

How much does a sample cost?

$20 per sample, which covers shipping it to you. Each sample stage — proto, fit and pre-production — ends in your written approval before anything moves forward.