Sampling and lead times

From an approved tech pack: proto 5–7 days, fit 3–5 days, PP 5–7 days, fabric booking and lab dips 10–15 days, and a full critical path of 45–65 days to ex-factory for orders of 2,000–10,000 pieces. Each stage ends in an approval — nothing moves forward until you sign it off. Samples cost $20 per sample, which covers shipping it to you.
The critical path, stage by stage
StageDurationWhat it depends on
Proto sample5–7 daysFrom an approved tech pack. First physical read on fit and construction.
Fit sample3–5 daysAfter your comments on the proto. More fit rounds extend this stage.
PP sample5–7 daysPre-production sample in bulk fabric and trims. Nothing is cut before you sign it off.
Fabric booking & lab dips10–15 daysStock fabric moves fast. Custom dye or print adds materially to this stage.
Bulk production to ex-factory45–65 days totalWhole critical path, for orders of 2,000–10,000 pieces. Larger orders sit at the upper end.

What actually moves these dates

Extends the schedule

  • Extra fit rounds — each one adds its own cycle
  • Custom dyeing or printing instead of stock fabric
  • Lab dip and strike-off re-approvals
  • Trims or hardware with their own lead time
  • Comments returned slowly — the clock is shared

Shortens it

  • A complete tech pack: measurements, BOM, artwork, label copy
  • Stock fabric in an available colour
  • Consolidated feedback in one round rather than three
  • Approving a counter-sample instead of re-specifying
Treat a single number as a warning sign. A supplier who answers "about 60 days" without naming the milestones has not planned your order — they have guessed. Ask any supplier, including us, what their lead time assumes about fabric availability and approval rounds.